Continue reading: The top 3 biggest forecasting and planning errors

The top 3 biggest forecasting and planning errors

In my consulting and training engagements I get to see the impact where planned delivery dates are missed. It’s never because people just aren’t trying or working hard enough. This post gives you my top 3 real reasons traditional Agile planning and the dates produced by them fail.

Number One Reason: The Assumed Start Date is Missed

Sounds obvious right. To give an estimated delivery date you add the estimated duration to a starting date. Rarely do I see anyone track or adjust for the eventual start date for any initiative. Often the definition of “started” isn’t clear. 

Continue reading